Fire station 3 has been open and staffed 24/7 since March 2023. Construction of station 3 started in early 2022 and completed in February 2023.
- 1 FireStation3Interior_13_Sylvester
- 2 FireStation3Interior_14_Sylvester
- 3 FireStation3Interior_15_Sylvester
- 4 FireStation3Interior_16_Sylvester
- 5 FireStation3Interior_18_Sylvester
- 6 FireStation3Interior_04_Sylvester
- 7 FireStation3Interior_05_Sylvester
- 8 FireStation3Interior_06_Sylvester
- 9 FireStation3Interior_07_Sylvester
- 10 FireStation3Interior_08_Sylvester
- 11 FireStation3Interior_09_Sylvester
- 12 FireStation3Interior_10_Sylvester
- 13 FireStation3Interior_11_Sylvester
- 14 FireStation3Interior_12_Sylvester
- 15 BudgetCoverOption_02_FireStation3
- 16 BudgetCoverOption_03_FireStation3
- 17 BudgetCoverOption_04_FireStation3
Construction Updates:
_________________________________________________________________
January 2, 2023 Update
- Landscaping finishes.
- Interior finishes in progress.
_________________________________________________________________
December 7, 2022 Update
- Concrete Driveway and Curbs.
- Interior finishes in progress.
- Garage Doors.
- Parking lot paving.
_________________________________________________________________
November 4, 2022 Update
- Roof trusses complete over the garage areas.
- Concrete Curbs and sidewalks started.
- Check back for interior photos coming soon...
_________________________________________________________________
September 19, 2022 Update
- Framing Completed
- Roof trusses complete over the office areas.
- Brick is complete.
_________________________________________________________________
August 24, 2022 Update
- Garage area block walls completed.
- Wall framing completed.
- Roof Truss in progress.
_________________________________________________________________
July 28, 2022 Update
- Wall Framing Started
_________________________________________________________________
July 4, 2022 Update
- Excavation work is complete
- Footers completed
- Concrete floors completed
________________________________________________________________
February 28, 2022 Update
- Final drawings approved for construction